วันเสาร์ที่ 31 ตุลาคม พ.ศ. 2558

Chao Phraya promenade hits hurdle !!!


 

Construction of the 14-billion-baht Chao Phraya promenade
 faces lengthy delays after efforts to conduct a feasibility study
tripped at the first hurdle.
Two of the three contractors that had expressed interest in
 bidding for the rights to the feasibility study have withdrawn
 from the race before it even started, said Pinit Lertudomtana,
 deputy chief of the BMA’s Department of Public Works.

 Mr Pinit said only one consortium, made up of Panya
 Consultants Co, Epsilon Co and Transconsult Co, had
submitted a formal tender.

The other two — Fusion Consultant Co and a consortium
consisting of Consultants of Technology Co, Consultant of
Architecture Co and COU Co — will not take part in the bid.

 Fusion Consultant Co did not  meet the qualifications to
 compete in the bid, while the other consortium failed to
 submit a proposal, said Mr Pinit, who is also a chairman
 of the panel responsible for awarding the contract.

As only one tender has been submitted, the panel will be
 forced to propose the cancellation of the bid to
 BMA executives.

The law stipulates that more than one candidate is required
 to ensure fair competition.

 It will now be up to the BMA executives to make a decision
on how to proceed with the project, Mr Pinit said.

The delay follows heavy criticism from activists and
 academics who say the 7km riverside promenade will damage
the environment, the livelihoods of local communities and the
 diversity of the riverside cultural landscape.

The project, dubbed the “New Landmark of Thailand”, will
 stretch on both sides of the Chao Phraya River, between the
Rama VII and Pin Klao bridges.

 The winner of the BMA contract would have been awarded
 120 million baht to conduct the feasibility study for the
 promenade and map out a master plan. Under the seven-month
 contract, the winner would have been required to study the
 impact of the project on the environment, city planning and
local livelihoods, as well as its effects on the flow of the
 country's main river system.

 An environmental impact assessment is required before
 approval for the project can be sought from the Office of
 Natural Resources and Environmental Policy and Planning.

 The winner would also have been required to craft the
 terms of reference for bidding on the contract to build
 the promenade.

 Mr Pinit said if a new round of bidding for the feasibility
 study is held, the terms of reference may have to be tweaked,
particularly the existing provision that says the qualified
 bidders must be companies registered with the Council of
 Engineers.

He conceded the provision had faced heavy criticism for
 excluding architectural firms from taking part.

 If BMA executives decide to launch a new request for tender,
 the provision may have to be erased to open the field to
 more candidates, Mr Pinit added.

The government called on relevant agencies to speed up their
work on the controversial project.

 Construction was initially scheduled to begin in January next
 year but had already been pushed back to June.

 

News,General,Bangkok Post, 1November 2015.

 

My question is why this project should run if it is not
 
feasible for any benefit to the country.

 

Sincerely Yours.

 

ไม่มีความคิดเห็น:

แสดงความคิดเห็น